Special Notice To SSPC QP 1 And QP 3 Certified Contractors
SSPC auditors are continuing to place special emphasis on QP 1
and QP 3 audit evaluation items that deal with clarification of
ambiguous, omitted or incorrect contract requirements as well as
notation and documentation of non-conforming work/deviations from
the specification.
If the contractor is authorized to perform work that deviates
from the specification the contractor's quality control (QC)
personnel
and QC Manager must document that fact by obtaining written authorization
or confirmation from the resident engineer or other authorized
facility owner representative of any changes, revisions, modifications
or
clarification of ambiguities. This documentation must be available
at the job site or quickly accessible to the job site (e.g. via
email; fax, etc). Otherwise the auditor has the authority to issue
a critical item deficiency which could place the contractor’s
certification status at risk.
If the contractor was given a “verbal” OK but has not
yet received written confirmation because the paper work hasn’t
caught up or was told that there would not be any written authorization
on the change, contractor QC personnel must document this by recording
the who, what, when, where, why and how of the change. SSPC suggests
you create and put in place a procedure for documenting “verbal” authorizations,
if you haven’t done so already.
In addition, contractors must also document specification deviations
in their daily QC/Work reports, regardless of whether the
change has been documented or verbalized. These daily reports
must
also be available at the job site for the auditor to review.
Examples of specification deviations that auditors run into
on job sites that are not always properly documented include
but
are not
limited to:
•
blast profiles outside of specified ranges
•
coating thickness outside of specified ranges
•
coating thickness not measured IAW PA 2 even though PA 2 is called
out in the specification
•
cleaning or coating outside of specified ambient condition ranges
•
substitution of materials
•
containment not designed or being operated according to approved
plans
•
omitting a process such as chloride testing or pressure washing
before painting
•
skipping a hold point inspection
•
changing a process
Another area of concern is when the auditor observes obviously
non-conforming work that is being accepted by the owner’s inspector or official
representative. For example, if the specification calls for blast
cleaning to SP-10 but the contractor is cleaning to SP-6, and there
is no formal variance (written or “verbal”) on record
allowing for the change, but the inspector is accepting the work,
expect the auditor to ask for an explanation. The auditor may also
report such a condition in the audit report as well as report the
finding to the facility owner.

|